Road reconstruction nears end, on schedule

Nothing beats the fresh smell of a new layer of asphalt!

The major reconstruction this year of several streets in the community is on schedule and has faced no unforeseen issues, writes the city’s supervising engineer, Kevin Gibbs (Kevin.Gibbs@ottawa.ca). “The project is currently on track to meet the project timelines,” he writes. “We do not anticipate any major unforeseen problems at this time.”

The work involved replacing 50-plus-year-old trunk sewers (sanitary and storm) and watermains along parts of Hilliard, Farlane and Wallford Way. The project began last year, with similar work occurring on parts of Deer Park, Millbrook and Hilliard.

The last phase of the 2020 work, the final paving of the three streets, was recently completed, and landscaping on those streets was completed earlier this summer.

“The bulk of the remaining underground and road work will be completed this fall, including any remaining concrete sidewalk work, with construction operations winding down after the end of November 2021.”

The rebuilt 2021 streets will receive an initial paving this fall, but the final asphalt, and landscaping, will be carried out in 2022. “Those activities are expected to resume in May and wrap up in June, based on the contractor’s current schedule, although some work could extend until the end of July. These construction operations are generally of shorter duration and less disruptive than the underground construction work was this year.”